EGNATIA HIGHWAY (4.2.2c): COMPLETION WORKS AT GREVENA-KOZANI

The project consists of the additional works in the 2nd subsection of Grevena-Kozani section, which includes the stabilisation of the landslides east of the T1 bridge (at Trombeta river) in the foundation of the abutment M2 of the T1 bridge, the remaining works for the construction of Technical Work T1, the application of the additional protection measures for the safety of the section of Grevena-Kozani National road that lies over the Egnatia Highway from km sta.11+300 up to sta.11+380, the restoration of the adjacent rural road network in the section from km sta.6+000 up to sta.18+840 of Egnatia Highway, and the construction of additional drainage works not covered by the Egnatia Highway area.

LocationGREECE, KOZANI
ClientEGNATIA ODOS SA
ContractorEKTER SA
Participation100%
Construction Period01/2001 - 01/2003
Project value2,623,000.00€
ObjectRoad rehabilitation and paving and asphalting works of the provincial road network over a length of 2.5 km.

Technical Data:

Prestresssed rock anchors (1200KN): 2,080 m

Road Pavement: 160.000 m2 (thickness 10cm) & Road Pavement: 60.000 m2 (thickness 23 cm)

Perforated drainage pipes: 2.500m

Earthworks volume: 106.000 m3